Express Global Logistics (EXG) has completed another challenging project logistics operation, showcasing our expertise in handling oversized and heavy cargo transportation. The recent multimodal shipment of critical processing equipment from a site located in the northwestern part of India to a port on the west coast demonstrates our commitment to delivering comprehensive end-to-end logistics solutions.
CARGO OVERVIEW
The shipment comprised two massive components:
- Ammonia Converter
- Dimensions: 30m (L) × 4.25m (W) × 4.9m (H)
- Weight: 530 metric tons
- Transport configuration: 22 side-by-side axle lines
- Ammonia Unitized Chiller
- Dimensions: 26m (L) × 4.5m (W) × 5m (H)
- Weight: 220 metric tons
- Transport configuration: 15 axle lines
SCOPE OF SERVICES
EXG’s comprehensive scope for this project included:
- Land transportation of both units from the workshop to a captive jetty
- Specialized loadout operations onto a 180-class cargo barge
- Professional sea fastening to ensure cargo stability during marine transit
- Barging from a captive jetty from the north west of India to a port on the west coast
- Complete project supervision and coordination
TECHNICAL EXECUTION
Our engineering team meticulously planned every aspect of this multimodal transportation:
Land Movement Phase: The initial phase involved transporting the massive converter and chiller units from the workshop to the captive jetty using specialized hydraulic axle trailers. The 530MT converter required 22 side-by-side axle lines to distribute the extraordinary weight, while the 220MT chiller was transported using 15 axle lines.
Preparation of jetty: Correct placement of the barge according to the tide and time is crucial to ensure we do not miss the tide.
Marine Operations: At the jetty, our team executed a precision loadout of both components onto a 180-class cargo barge. Our experienced marine engineers implemented comprehensive sea fastening protocols to secure the cargo for the subsequent sea journey to the northwestern part of India. Since this was a beaching operation, it was critical to adhere to the tidal variations and complete load out in the required time lines. The roll-on operations were flawless and all timeframes were met resulting in successful loadout.
OVERCOMING CHALLENGES
This project presented several significant challenges that our team successfully navigated:
- Dimensional Complexity: The extraordinary dimensions of both components required specialized equipment and careful route planning to ensure safe passage.
- Timeline Coordination: Our project managers worked diligently to synchronize the transportation schedule with concurrent civil work at various locations.
- Infrastructure Modifications: Temporary road developments were necessary to accommodate the oversized cargo, particularly for the 30-meter converter.
- Electrical shutdown: EXG coordinated with local authorities for temporary electrical shutdowns along the route to avoid overhead obstructions.
This successful project further solidifies Express Global Logistics’ position as a leader in project cargo logistics for the energy and industrial sectors. Our ability to provide integrated solutions from engineering studies and route surveys to specialized transport and installation continues to make us the partner of choice for handling India’s most challenging logistics projects.